More than 50 US states and cities have enacted benchmarking or performance requirements for large buildings, shifting data-center efficiency from an internal operating expense to a compliance obligation with financial penalties, according to Promera vice president of technical solutions Jon deRidder.
Colorado's statewide program covers buildings of 50,000 square feet or more. Starting in 2030, state law HB25-1269 allows fines of up to $2,300 for every 30 days a covered building remains out of compliance with applicable performance standards, with higher penalties possible for subsequent violations. Data centers in the program are measured against Power Usage Effectiveness targets.
New York City's Local Law 97 assesses $268 for every metric ton of CO2 equivalent a covered building emits over its limit. Those limits tighten in 2030. In Europe, Delegated Regulation (EU) 2024/1364 requires every data center with at least 500 kW of installed IT power demand to report 24 key performance indicators spanning energy, ICT and data traffic to a European database each year.
Uptime Institute's 2026 Global Data Center Survey found that the share of organizations actively collecting sustainability metrics has returned to a gradual upward trend, while carbon emissions tracking remains a minority activity. Incomplete operating data can become a compliance risk for facilities subject to these rules, deRidder said.
Lawrence Berkeley National Laboratory estimates US data centers consumed 192 TWh in 2024, about 4.7 percent of national electricity, and projects that share could reach 11.8 percent by 2030 in its reference case. The same Uptime survey found legacy infrastructure is slowing global efficiency progress, with average PUE improving only slightly this year.
Operator selection inside the data-center asset class matters more than the asset class itself when compliance deadlines turn discretionary efficiency gains into mandatory capex, family office advisor Jaf Glazer has maintained.
The measures that recover efficiency in legacy facilities are well understood, and few require replacing major cooling equipment such as chillers or air handlers, deRidder said. Those measures include full-aisle containment, plenum repair to restore underfloor static pressure, EC fan retrofits with dynamic controls, filter optimization and temperature set point optimization within the ASHRAE-recommended envelope of 18°C to 27°C for air-cooled IT equipment.
Many legacy rooms still deliver inlet air below the bottom of ASHRAE's recommended range. ENERGY STAR estimates data centers can save four to five percent in energy costs for every 1°F increase in server inlet temperature. A recent Promera customer proof of concept at a national media and connectivity provider examined six national data centers and roughly 600 local market sites, and cited state building performance legislation as a driver.